Since our last report, our crews been onsite working on detail work on the flat roof which included coating the pop-up walls and pressure washing finished areas. They also completed the removal and installation of the new membrane on the top of the sloped roof.
The crews been onsite continuing with the removal of the old roofing system on the flat roof. They have completed an additional 5,300 SF and 80 LF of flashing. They have also installed 300 LF of the sheet metal. We are not approx. 89% complete with the flat roof section.
Drone video of the roof work: Click Me
Our crews been onsite this week where they have continued with the removal of the old roofing system on the flat roof. They completed a 1,400 SF section as well as completed 80 LF of flashing. We are also in receipt of the approved change order for the TPO and will begin the work on the top of the shingle roof at the Chapel.
Our crew returned to the job-site yesterday where they continued with the tear off on the flat roof section. They did encounter 32 SF of deteriorated decking that was replaced along with 30 LF of 2x6 wood that was in need of replacement. The contract does have a plywood allowance of 800 SF and so far only 260 SF has been replaced.
Our Savior Lutheran Church! Our crew has been working on the sloped roof where they have installed 5,300 SF of the new shingles. They are approx. 90% complete with the shingle section and have been making great progress with the project overall!
Percent Complete: 60%
Our crew has continued on the flat section where they removed and replaced another section of the old roofing system and installed the insulation and membrane. They did encounter 32 SF of deteriorated plywood decking that was replaced which falls under the deck allowance. We also had our sheet metal crew onsite installing the eave drip metal on the shingle roof.
Started tearing off the first section of the flat roofs and installed TPO roof covering.
Comments
Good morning Our Savior Lutheran Church. Our crew has started with the tear off on the Shingle section of the roof and have removed and replaced a total of 3,400 SF of the old roofing system and installed the new under-layment. Due to the steep slope of the Church, the crew is taking extra time with the removal process and ensuring that their safety and for the ones around them comes first.
Comments
Good afternoon Our Savior Lutheran Church! Our crew has continued with the removal of the old roofing system over the Metal panel section and have installed 1,800 SF of the under-layment. They also came across a total of 160 SF of deteriorated plywood decking and two 2x4 pieces of wood that was in need of replacement. You will find below a plywood deck replacement log that we will keep as an on-going change order per the Contract and the Unit prices below along with the photos. The crew also started working on the pop up roof section where they removed and replaced 600 SF. Please contact us with any questions, thank you.